9.4. FLOW SWITCH/LEvEL SWITCH

In certain countries there is a requirement that the heat pump must
be equipped with a level switch for the brine system. Always check
local rules and regulations before commissioning the heat pump.
1
2
3
Figure 62: Level switch in the expansion tank/bleed tank.
Figure 63: Connection diagram for the flow switch or level switch.
Connect the flow switch or level switch to terminal blocks 217 and 219.
l

9.5. HIGHER HOT WATER TEMPERATURE

Does not apply to models with refrigerant R134a,
!
models Geysir with Passive cooling -4H, -5H and -7H.
NOTE! Never connect the heat pump to provide a
!
higher temperature unless the heating or hot water
systems require it. Higher temperatures increase the
load on the heat pump.
If necessary, the heat pump can be connected to produce hotter
water for the heating system and hot water system when it is
installed.
B
Figure 64: The pressure switches are installed
on the compressor's pressure pipe.
26
ENGLISH
Q
Safety valve
W
Level switch
E
Floats
A
Move the grey cables, which are normally connected to pressure switch
l
A, to pressure switch B.

10. START UP

NOTE! Read the safety instructions!
The installation may only be commissioned if the heating
!
system, water heater and brine system have been filled and
bled. Otherwise the circulation pumps may be damaged.
If the installation is only to be run on auxiliary heating, first ensure
!
that the heating system is filled and bled and that neither the
brine pump nor the compressor can be started. This is carried
out by setting the operating mode to ADD.HEAT.
Any alarms that may occur in connection with the installation
!
can be fault-traced in the "Troubleshooting" section in the
service instructions.

10.1. INSTALLATION CHECkLIST

Before manual test operation check the following points:
Piping installation, heating system
n
Line connections in accordance with the connection diagram.
l
Flexible hoses on the supply and return lines
l
Pipe insulation
l
Strainer on return line, heating system
l
Bleeding of the heating system
l
All radiator valves fully open
l
Expansion tank, heating system (not included in the delivery)
l
Safety valve for expansion tank (not included in the delivery)
l
Filler cock heating system (not included in the delivery)
l
If a an external water heater is installed, also check:
Exchange valve
l
Safety valve for cold water (9 bar)
l
Electrical Installation
n
Circuit-breaker
l
Fuse protection
l
Direction of rotation of the compressor
l
Coolant pump
l
Geysir Air, outdoor unit
l
Geysir Air, defroster sensor
l
Positioning of the outdoor sensor
l
Control computer settings
l
If a an external water heater is installed, also check:
Exchange valve