Installing the boiler

Fig. 7
Transporting the boiler using pipes
[1]
Positions for securing the boiler against slipping
[2]
Pipe (for carrying)
3.2

Transporting the boiler on rollers

If the route to the installation site is flat, the boiler can also be rolled. This
requires at least 5 lengths of pipe approx. 28 inches long (diameter
1¼ ") to be placed underneath to act as rollers.
▶ Lay the lengths of pipe on the floor spaced about 16 inches apart.
▶ Lift the boiler onto the lengths of pipe and carefully transport it to the
installation site.
You can also use standard transport rollers.
▶ So that the bottom plate is not pressed in, it is
essential to ensure that the weight is evenly
distributed across the load-bearing parts.
Fig. 8
Transporting the boiler on rollers (dimensions in inches)
14
4
Installing the boiler
This chapter details how to install and site the boiler correctly in the
installation room.
4.1

Installation room requirements

7 747 010 720-07.1RS
4.2

Recommended wall clearances

When determining the installation location, take the clearances for the
flue gas routing and the connection pipes into consideration ( Fig. 9,
page 15 and Section 6, page 16, venting system connection and the
piping on the water and gas sides).
Dimension
A
1)
B
C
D
1)
E
Table 6 Recommended and minimum wall clearances (dimensions in
inches). Minimum clearance dimension E must absolutely be
adhered to.
1) This clearance depends on the venting system installed
7 747 010 720-08.1RS
WARNING: Risk of system damage due to freezing!
▶ Install the heating system in a frost-free room.
DANGER: Dangers posed by explosive and easily
combustible materials.
▶ Never use or store easily flammable materials (paper,
curtains, clothing, thinners, paints etc.) near the
boiler.
▶ Maintain a clearance of 16 inches from the boiler.
WARNING: Risk of boiler damage through contaminated
combustion air.
▶ Do not use cleaning agents that contain chlorine or
halogenated hydrocarbons (e.g. in spray cans,
solvents and cleaning agents, paints, glues).
▶ Never use or store chlorinated cleaning agents or
halogenated hydrocarbons in the installation room.
▶ Avoid excessive dust accumulation (building dust) on
or near the boiler.
Wall clearance (inch)
Minimum
20
22
20
20
6
Allow extra wall clearances for additional components,
for example, indirect water storage tanks, pipe
connections or other components on the flue gas side
etc.
Logano plus GB312 – 6 720 806 273 (2013/01)
Recommended
28
28
28
28
14

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents