Connecting The Boiler To The Heating System; Installing B-Kit - Buderus Logano plus GB312 Installation And Service Instructions Manual

Gas condensing boiler
Table of Contents

Advertisement

6
Installing the boiler
6.9.2

Connecting the boiler to the heating system

CAUTION: Risk of system damage due to leaking
connections!
▶ Connect system pipes without stress to the boiler
connections.
Boiler
Boiler supply (VK)
Boiler return (RK)
90-4 to 280-8
NPT 2½ "
Table 11 Water connection sizes
VK
RK
Fig. 23 Water connection
RK
Boiler return
VK
Boiler supply
AL
Air Inlet Connection
6.9.3

Installing B-Kit

The pressure relief valve, the temperature/pressure gauge and the
check valve are connected to the boiler supply VK by means of the supply
manifold (included in B-kit).
CAUTION: Risk of system damage due to an incorrectly
installed B-kit or failure to install check valve.
▶ Make sure that the non-return check valve is fitted
correctly (observe arrow). The arrow indicates the
direction of flow. The non-return check valve
prevents water flow in the opposite direction to the
arrow.
▶ Install the B-kit including check check valve, with the direction of flow
away from the boiler (observe arrow on check valve).
▶ Align the B-kit so that the temperature/pressure gauge is oriented
horizontally with respect to the outside of the boiler and the pressure
relief valve points upwards ( Fig. 24).
▶ Insert seal in flange joint and tighten evenly.
We recommend installing an automatic air vent after the
B-kit on the supply pipe.
24
AL
▶ Use the NPT double union supplied to install and seal the safety valve
in the connection provided ( Figs. 23 and 24).
▶ Install and seal the temperature/pressure gauge in the connection
provided ( Fig. 24).
Any additional safety devices required can be installed and sealed in
the remaining connections. Follow the manufacturers' instructions.
VK
10
8
11
Fig. 24 Installing B-Kit
VK
Boiler supply
[1]
Nut and washer 4x
[2]
Check valve 1x
[3]
Supply pipe (external)
[4]
Screw 4x
[5]
Washer 4x
[6]
NPT thread (on external supply pipe)
[7]
Gasket 2x
[8]
Gasket 1x
[9]
Threaded flange, 2½ " x 2½ ", NPT
[10] Pressure relief valve (safety valve)
[11] Pressure/temperature gauge
If a high limit safety cut-out is installed according to
ASME-CSD1 on the heating supply of the (B-kit), heed
the following:
▶ At the factory, a pump post-purge time of 5 minutes
is set on the BC10 controls. This value can be
increased but not reduced.
▶ If an external controller controls the recirculation
pump, a pump post-purge time of 5 minutes must be
ensured.
▶ Close off unused connections with ¾ " NPT plugs and
seal.
▶ Be sure to install a blow-off tube to the pressure relief
valve installed in the B-Kit.
CAUTION: Risk of system damage due to incorrect
installation!
▶ Make sure that the B-kit, including pressure relief
valve and check valve, is correctly connected and not
omitted from the boiler supply VK.
Logano plus GB312 – 6 720 806 273 (2013/01)
1
2
5 4
NPT
7
9
6
3
7 747 010 720-03.1RS

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents