6.4.8 Charger Control

To turn an individual UPS battery charger on:
1.
Select the CONTROLS symbol on the main menu bar on the UPS requiring the charger to be turned on. The
System Control screen is displayed.
2.
Select Battery on the System Control screen
3.
On the Battery System Control screen, select the RESTING
RETURN pushbutton.
To turn an individual UPS battery charger off:
1.
Select the CONTROLS symbol on the main menu bar on the UPS requiring the charger to be turned off. The
System Control screen is displayed.
2.
Select Battery on the System Control screen.
3.
On the Battery System Control screen, select the CHARGING
RETURN pushbutton.

6.4.9 Battery Test

NOTE 1
This UPS has a user initiated battery test intended to determine if the batteries are
able to support the load.
The battery test is only able to be initiated when the battery is fully charged. This
NOTE 2
normally occurs within 72 hours of the start of a charging cycle. The command will
not be shown if the test is not able to be run.
To start an individual UPS battery test:
1.
Select the CONTROLS symbol on the main menu bar on the UPS to be tested. The System Control screen
is displayed.
2.
Select Battery on the System Control screen.
3.
On the Battery System Control screen, select the RESTING
RETURN pushbutton.
CHARGING command, then press the
TESTING command, then press the
Eaton 9E UPS (80-200 kVA, 380/400/415V) Installation and Operation Manual
UPS Operating Instructions
RESTING command, then press the
6-21

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

93e

Table of Contents