If installing Battery cabinets, proceed to paragraph 2.3 for Battery cabinet
installation and then proceed to paragraph 2.4 for Options cabinet installation;
otherwise, proceed to paragraph 2.4.
16.
Using retained hardware, reinstall shipping brackets previously removed to
front and rear of Options cabinet with the angle facing outward (see Figures
2---3 and 2---4).
17.
Secure Options cabinet to floor with contractor supplied hardware.
18.
If installing Battery cabinets, proceed to paragraph 2.3 for Battery cabinet
installation and then proceed to paragraph 2.4 for Options cabinet installation;
otherwise, proceed to paragraph 2.4.
2.2.3
Unloading the Powerware 9330 (25 kVA---40 kVA) UPS
Cabinet from the Pallet
The UPS cabinet is bolted to a wooden pallet supported by wood skids. To
remove the pallet, perform the following procedure:
WARNING:
The UPS cabinet is heavy. Refer to Drawing 164201300- -3 in Appendix A for
weight of cabinets. If unloading instructions are not closely followed, the
cabinet may cause serious injury.
CAUTION:
Do not tilt cabinets more than 10 degrees from vertical.
1.
Use a forklift or other material handling equipment to move the cabinet to the
installation area. Insert the forklift jacks between the skids on the bottom of
the unit.
2.
Remove left front solid panel, and front vented panels from UPS cabinet. Front
panels are secured with magnetic latches and are removed by pulling panels
straight forward to disengage magnetic latches (see Figure 2---5).
3.
If the leveling feet are not fully retracted, turn the leveling feet until they are
retracted.
4.
Remove four bolts, (1) in Figure 2---6, securing the rear shipping bracket (3) to
the cabinet and four bolts (2) securing the bracket to the pallet. Remove the
rear shipping bracket. If installing cabinet permanently, retain shipping
brackets and securing hardware for later use.
5.
Remove four bolts, (1) in Figure 2---5, securing front shipping bracket (3) to the
pallet. Do not remove bolts (2) securing the bracket to the cabinet.
6.
Remove four bolts, (4) in Figure 2---6, securing removable skid (5) and
remove skid.