8.
Remove three bolts, (2) in Figure 2---1, securing front shipping bracket to the
cabinet.
9.
If installing cabinet permanently, retain shipping brackets and hardware;
otherwise, discard or recycle the pallet and brackets in a responsible manner.
10.
Roll cabinet to final installation location.
11.
If permanently mounting the system, proceed to step 15; otherwise, proceed to
step 12.
12.
If installing a Remote Battery System, proceed to paragraph 2.2.3; otherwise,
proceed to step 13.
13.
Secure the UPS cabinet in position by lowering the leveling feet, until cabinet is
not resting on the casters and the cabinet is level.
14.
If installing Battery and Options cabinets, repeat steps 1 through 10 for
remaining cabinets and proceed to paragraphs 2.3 and 2.4; otherwise,
proceed to paragraph 2.2.5.
15.
If installing a Remote Battery System, proceed to paragraph 2.2.3; otherwise,
proceed to step 16.
16.
Using retained hardware, reinstall shipping brackets previously removed to
front and rear of UPS cabinet with the angle facing outward.(see Figures 2---1
and 2---2).
17.
If installing Battery and Options cabinets, repeat steps 1 through 10 for
remaining cabinets and proceed to paragraphs 2.3 and 2.4; otherwise,
proceed to step 18.
18.
Secure cabinet to floor with contractor supplied hardware and proceed to
paragraph 2.2.5.
2.2.2
Unloading the Powerware 9330 (25 kVA---40 kVA) UPS
Cabinet from the Pallet
The UPS cabinet is bolted to a wooden pallet supported by wood skids. To
remove the pallet, perform the following procedure:
WARNING:
The UPS cabinet is heavy. Refer to Drawing 164201300- -3 in Appendix A for
weight of cabinets. If unloading instructions are not closely followed, the
cabinet may cause serious injury.
CAUTION:
Do not tilt cabinets more than 10 degrees from vertical.
1.
Use a forklift or other material handling equipment to move the cabinet to the
installation area. Insert the forklift jacks between the skids on the bottom of
the unit.
2.
Remove left front solid panel, and front vented panels from UPS cabinet. Front
panels are secured with magnetic latches and are removed by pulling panels
straight forward to disengage magnetic latches (see Figure 2---3).
3.
If the leveling feet are not fully retracted, turn the leveling feet until they are
retracted.