Requirements
The required software was installed on the PG/ PC or PCS 7 ES.
Procedure for configuring and assigning parameters
1. Start the SIMATIC Manager.
2. Configure the ET 200iSP with HW Config.
– Create a new project
– Drag modules from the hardware catalog to the configuration table
3. Configure the time stamping (option).
4. Double-click the first module of the ET 200iSP in the configuration table and set the
parameters.
5. Parameterize the other modules of the ET 200iSP.
6. Save the configuration or download the configuration (e.g. typically to the CPU 410-5H):
– Configuration with IM 152-1PN: In the IO controller
– Configuration with IM 152-1DP: In the DP master.
7.4

Project Engineering with GSD File and SIMATIC PDM

Integration of the station
The integration of the station into the automation system depends on the type of network used:
• When connected via PROFINET IO, the station is integrated as an IO device with an interface
module IM 152-1PN.
• When connected via PROFIBUS DP, the station is integrated as a DPV0/DPV1 device with an IM
152-1DP interface module.
ET 200iSP
Operating Instructions, 11/2022, A5E00247483-AK
7.4 Project Engineering with GSD File and SIMATIC PDM
Commissioning and Diagnostics
161

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents