6 Remove all wires on the left hand side and upper side from the wire clips and
leave them aside.
7 On the right hand side, remove all wires for which a connector was unplugged
from the wire clips and push these wires through the hole to the back side of
the mounting plate.
INFORMATION
The power supply cables (from the power supply wire terminal to the noise filter
PCB) can stay in the wire clips.
DANGER: RISK OF ELECTROCUTION
Confirm the rectifier voltage is below 10 V DC before proceeding, see
rectifier
voltage" [
8 Remove the cover of the compressor wire terminals.
a
a
Compressor wire terminals cover
9 Disconnect the Faston connectors from the compressor wire terminals U, V
and W.
INFORMATION
Note the position of the Faston connectors on the compressor wire terminals to
allow correct connection during installation.
4
 135].
"To check the
RZA200+250D7Y1B
Sky Air Advance-series
ESIE19-13A – 2020.05

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sky air advance rza250d7y1b

Table of Contents