Step 12: Roof Framing
You will need for this page:
(QTY: 12)
1
Seal the gap between the Gables
using the weather stripping tape as
shown. Do this at both ends of the
building before installing Roof Beams.
2
Position the Roof Beams as shown
below and install using two (2) bolts
and nuts per side. Install the Main
(center) Beam fi rst.
Top View of Gables
Weather Stripping Tape
Beam End Views
Angled side of Beams must face up.
Assemblies from Step 3:
Main Roof Beam Assembly (1)
Single Roof Beam Assemblies (2)
Tape should wrap around gap between Gables.
Tape BOTH Gable joints before installing Roof Beams.
31