Hussmann Self-Contained Refrigeration Equipment Start Up Check List
***Please note that failure to follow this start-up document may void your factory warranty***
Step
Locate, read and keep install/operation manual in a safe place for
1
future reference.
2
Examine unit. Confirm there is NO damage or concealed damage.
3
Level the unit, side to side and front to rear.
4
Remove all shipping brackets/compressor straps/bolts etc.
Unit must be run on a dedicated electrical circuit. Do not use
5
adapters.
Ensure that the proper electrical requirements for the equipment are
6
supplied.
Verify all electrical wiring is secured and clear of any sharp edges or
7
hot lines. Connect plug to the outlet.
Some water should be placed in the drain to close the siphon and
8
prevent formation of ice.
9
Confirm drain trap is secure. Prime drain to prevent air entering case.
10
Verify all required clearances on the sides and back of unit.
Verify there are no air disturbances external to the unit. Heat and air
11
registers, fans, and doors etc.
Advise owner/operator that merchandiser must operate at temperature for 24 hrs prior to loading
with product.
LEGAL DISCLAIMER:
Hussmann shall not be liable for any repair or replacements made without the written consent of Hussmann, or when the product is installed or operated in a manner
contrary to the printed instructions covering installation and service which accompanied such product.
HUSSMANN CORPORATION • BRIDGETON, MO 63044-2483 U.S.A.
START UP / OPERATION
Startup Activity
Check
Island Self Contained R-290
3-1