Unpacking the Switch

3.2
UNPACKING THE SWITCH
Unpack the switch as follows:
1. Open the box and remove the packing material protecting the switch.
2. Verify the contents of the carton as listed in
Table 3-1 Contents of Shipping Carton
Item
1G694-13
Antistatic Wrist Strap
DB9 to RJ45 Adapter
Rackmount Kit
Manual Accessory Kit
Power Cord
3. Remove the tape seal on the non-conductive bag to remove the switch.
4. Perform a visual inspection of the device for any signs of physical damage. Contact
Enterasys Networks if there are any signs of damage. Refer to
3.3

INSTALLING OPTIONS

Note: If you are installing the 1G694-13 in a rack, it is recommended that you install an optional
Ethernet expansion module or Mini-GBIC in the 1G694-13 first.
Caution: The expansion module is NOT hot-swappable. The switch must be powered down
before the expansion module is installed or removed. Hot-swapping the expansion module while
the switch is powered on could cause the device to stop forwarding frames.
The 1G694-13 has one expansion slot for an optional 10-Gigabit Ethernet expansion module and
four expansion port slots for optional Mini-GBICs. For instructions to install an Ethernet
expansion module, proceed to
3-2
Hardware Installation
Table
Section
3.4. To install a Mini-GBIC, proceed to
3-1.
Quantity
1
1
1
1
1
2
Section 1.6
for details.
Section
3.5.