INSTALLATION SEQUENCE

The typical sequence of installation is outlined below; however, each installation is unique and may result in
variations to the steps described.
See the pages referenced in the following steps for detailed instructions.
Framing
1. Construct the Fireplace Framing (Page 17).
2. Prepare the Fireplace Top Spacers (Page 19).
3. Route the Gas Supply Line to the Fireplace (Page 19).
4. Determine Venting in Combination Venting Fireplaces (Page 20) *.
5. Install Non-Combustible Front Fireboard Standoff (Page 20)
6. Rough in the Electrical Supply, if Needed (Page 21).
7. Place the Fireplace in the Framing and Secure (Page 21).
Venting
8. Select a Horizontal or Vertical Vent System (Page 22).
9. Install the Vent Restrictor (if necessary) (Page 23).
10. Connecting the Vent Pipe (Page 24).
11. Install the Vent System (Page 27).
Electrical Connection
12. Complete the Field Wiring (Page 40).
Gas Connection
13. Connect the Gas Line (Page 43).
14. Verify Proper Fireplace Operation (Page 44).
Remote Control
15. Initialize the Remote Control System for the First Time (Page 45)
Finishing
16. Install the Firebox Liners (required on DRT4200-C models, Page 46).
17. Install the Logs, Volcanic Stone, and Glowing Embers (Page 46).
18. Install the Glass Door (Page 46).
19. Adjust the Air Shutter to Ensure Proper Flame Appearance (Page 46).
20. Install the Hood (Page 48).
21. Reinstall the Included Barrier (Page 48).
22. Install the Finishing Materials (Page 48).
23. Attach the Safety-in-Operation Warning Labels (Page 48).
* The 45" models are top vent only.

Construct the Fireplace Framing

1.
1. Frame the fireplace as illustrated in Table 10, Page 18. For corner framing installations, use Table 11. All
framing details must allow for a minimum clearance to combustible framing members as shown in Table 8,
Page 15.
2. If the fireplace is to be elevated above floor level, a solid continuous platform must be constructed below the fireplace.
NOTE: Headers may be in direct contact with the fireplace top standoff spacers when they are bent up vertically,
maintaining the 4" clearance to the fireplace top, but must not be supported by them or notched to fit around them.
All construction above the fireplace must be self-supporting. DO NOT use the fireplace for structural support.
Installation
901032-00B, 07/2020
17

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents