Installation - Mechanical

Base with Turned-Up Floor

Note: Corner gussets are to ensure unit squareness
during shipping, lifting, and assembly. Please
remove, when unit is set in place.
1. Apply 4-inch x ¼-inch neoprene gasket to the full
perimeter face of each shipping split section.
2. Join the two sections and secure with field-provided
5/8-inch flat washers and 5/8-inch x 2 ½-inch grade 9
bolts through each of the six holes.
3. Apply a heavy bead of caulk to the inside of the
U-channel.
Figure 17. Add caulk to U-channel
Cap
Caulk
Floor
4. Press U-channel down over upturned flanges with
moderate pressure to ensure it is fully seated onto
upturned flanges. The caulk will cure and act as an
adhesive to hold U-channel in place, no fasteners are
required.
20
Figure 18. Press U-channel in place
Floor
Floor
Cap
Caulk
Gasket
Gasket
Floor
CLCH-SVX010A-EN