Figure 4.
Use proper lifting and rigging methods
When hoisting the unit into position, use the proper
rigging method, such as straps, slings, spreader bars,
or lifting lugs for protection and safety.
Make the loop of the sling parallel to the direction of
airflow whenever possible.
Each of the cables used to lift the unit must be capable
of supporting the entire weight of the unit.
The air handler is not designed to be lifted, rigged or
ceiling suspended from the top of the unit.
Never lift units in windy conditions. Personnel should
be positioned overhead and on the ground to guide the
crane or helicopter operator in positioning the
sections.
Never stack the pipe cabinet and inlet hoods on the unit
as the unit is being lifted.
Do not attach the intake/exhaust hoods to the unit prior
to lifting the unit. Doing so may damage the
equipment. Attach the hoods to the unit only after all
sections are in place.
Remove all wooden blocks before installing the unit to
the roof curb.
CLCH-SVX010A-EN
All shipping supports and crating on the face of the
sections must be removed to permit proper fit-up and
sealing of the surfaces. Dispose of properly.

Hoods and Pipe Cabinets

WARNING
Risk of Unit Dropping!
Always place, assemble, and suspend modules/
subassemblies one at a time. Placing, assembling, and/
or suspending more than one module/subassembly at
a time could result in module/subassemblies dropping
and crushing technicians which could result in death,
serious injury, or equipment damage.
When hoisting inlet and exhaust hoods into position, use
the proper rigging method such as straps, slings, or
spreader bars for protection and safety. Inlet and exhaust
hoods will either ship inside the unit if space permits, or
separately on a wooden pallet. Separately shipped hoods
should be hoisted separately from the unit. Hoods inside
the unit may be hoisted while inside the shipping section,
as long as they are secured for the lift such that they cannot
shift and slide out.
Figure 5.
Lifting pipe cabinets
Rigging and spreader
bar provided by
contractor
Recommended
attachment to
lifting lugs

Unit Placement and Assembly

If the air handler ships in subassemblies or in individual
sections, some assembly is required.
Prior to unit assembly, refer to the unit submittal drawings
and unit tagging for correct placement of sections. Failure
to review the submittal drawings could result in
performance or assembly problems. If there are any
discrepancies, contact your local Trane sales
representative before proceeding.
Installation - Mechanical