Siemens SIMOTION D410 Series Commissioning Manual page 163

Hide thumbs Also See for SIMOTION D410 Series:
Table of Contents

Advertisement

Overview
The exact procedure when replacing or updating components depends on various factors.
If a project is updated, the procedure depends on the scope of change of the versions.
● Change of the SIMOTION main version
● Change of the SIMOTION service pack or hotfix version
● Change of the PROFINET version
● Change of the SINAMICS version
If another SIMOTION controller is to be used, then the procedure depends on whether a
device or a platform replacement is required.
Examples of upgrade scenarios are listed in the following overview table. They are shown in
the columns. The lines list the principle measures that have to be performed. Whether the
measure has to be performed in a specific case, must be decided project-specifically.
Grayed-out cells mean that a measure is not required.
Note
If the version is changed and the SIMOTION controller replaced at the same time, then all
measures apply; the measures must be performed in the TOP-DOWN sequence according
to the table.
SIMOTION D410
Commissioning Manual, 02/2012
(There are SIMOTION versions that contains several SINAMICS versions for a device)
Maintenance and service
5.1 Overview
163