Checklists prior to mounting

Note
Required checks
The checklists below do not purport to be complete. It may be necessary to perform
additional checks and tests in accordance with the situation specific to the particular
installation site.
Assemble the motor as described in the following chapters of the operating instructions.
Thoroughly familiarize yourself with the safety instructions and observe the checklists below
before starting any work.
Table 5- 1
Are all of the necessary components of the configured drive line-up available, correctly
dimensioned, installed and connected?
Are the environmental conditions in the permissible range?
Table 5- 2
Is the motor free of visible damage?
Have the mounting surfaces (e.g. flange, shaft) on the customer machine and on the
motor been cleaned?
Are the mounting surfaces free of corrosion?
Do the mounting dimensions (e.g. shaft diameter, shaft length, true run) on the cus-
tomer machine meet the specification?
S-1FK7 DYA G2 synchronous motors with planetary gearbox
Operating Instructions, 05/2018, A5E44881183B AA
Checklist (1) - general checks
Checklist (2) - checks regarding the mechanical system
Check
Check
Mounting
5.2 Checklists prior to mounting
OK
OK