Commissioning

Comply with the following when carrying out any work on the machine:
• Comply with the general safety instructions (Page 15).
• Comply with the applicable national and sector-specific regulations.
• When using the motor within the European Union, comply with the specifications laid down
in EN 50110‑1 regarding safe operation of electrical equipment.
Note
Service Center
Please contact the Service Center (Page 117) if you require commissioning support.
7.1

Measures before commissioning

Risk of losing the IP degree of protection as a result of damaged shaft sealing rings
This can result in death, serious injury, or material damage.
• Replace damaged components immediately.
7.1.1

Checks prior to commissioning

The following list of checks to be performed prior to commissioning does not claim to be
complete. It may be necessary to perform additional checks and tests according to the specific
plant or system.
Once the system has been correctly installed, check the following prior to commissioning:
• The machine is undamaged.
• The machine has been properly installed and aligned.
• The output transmission elements are set correctly for their type,
e.g. alignment and balancing of couplings, belt forces in the case of a belt drive, tooth forces
and tooth-flank backlash in the case of geared output, radial and axial clearance in the case
of coupled shafts.
• All fixing screws, connection elements, and electrical connections have been tightened to
the specified tightening torques.
• The operating conditions match the data provided in accordance with the technical
documentation, such as degree of protection, ambient temperature, etc.