Quick Configuration
To verify that the ISDN parameters were stored correctly,
Verifying
you must power-down and power-up the Switch Module.
Configuration
See steps below.
NOTE: Before powering-down the Switch Module,
Powering Up/
ensure that you are offline.
Down
1.
2.
3.
4.
After the powering-up, your Switch Module LED should
blink a three green flash sequence, indicating it is now
configured.
ISDN DEFINITY® Extender 2300EU/2100EU
Unplug the AC adapter from the back of the Switch
Module.
Disconnect the ISDN line and ECS digital port.
Reconnect the ISDN line and ECS digital port.
Plug the AC adapter to the back of the Switch
Module.