Powerware 9330 Installation And Operation Manual page 34

10 kva -- 20 kva 25 kva -- 40 kva
Table of Contents

Advertisement

4.
Remove four bolts, (1) in Figure 2---4, securing the rear shipping bracket (3) to
the cabinet and four bolts (2) securing the bracket to the pallet. Remove the
rear shipping bracket. If installing cabinet permanently, retain shipping
brackets and securing hardware for later use.
5.
Remove four bolts, (1) in Figure 2---3, securing front shipping bracket (3) to the
pallet. Do not remove bolts (2) securing the bracket to the cabinet.
6.
Remove four bolts, (4) in Figure 2---4, securing removable skid (5) and
remove skid.
NOTE: In the following step the pallet will tilt and act as a ramp once the cabinet is
rolled beyond the the center of the pallet. Make sure to restrain the cabinet
as it continues to roll down the pallet/ramp. The front shipping bracket will
act as a brake to assist restraining the cabinet.
WARNING:
Do not stand directly behind the pallet while unloading the cabinet If
unloading instructions are not closely followed, the cabinet may cause
serious injury.
7.
Slowly roll the cabinet toward the rear of the pallet. Once the pallet tilts,
continue rolling the cabinet down the pallet until the cabinet is clear of the
pallet.
8.
Remove four bolts, (2) in Figure 2---3, securing front shipping bracket to the
cabinet.
9.
If installing cabinet permanently, retain shipping brackets and hardware;
otherwise, discard or recycle the pallet and brackets in a responsible manner.
10.
Roll cabinet to final installation location.
11.
If permanently mounting the system, proceed to step 15; otherwise, proceed to
step 12.
12.
If installing a Remote Battery System, proceed to paragraph 2.2.4; otherwise,
proceed to step 13.
13.
Secure the UPS cabinet in position by lowering the leveling feet, until cabinet is
not resting on the casters and the cabinet is level.
14.
If installing Battery and Options cabinets, repeat steps 1 through 10 for
remaining cabinets and proceed to paragraphs 2.3 and 2.4; otherwise,
proceed to paragraph 2.2.5.
15.
If installing a Remote Battery System, proceed to paragraph 2.2.4; otherwise,
proceed to step 16.
16.
Using retained hardware, reinstall shipping brackets previously removed to
front and rear of UPS cabinet with the angle facing outward.(see Figures 2---3
and 2---4).
17.
If installing Battery and Options cabinets, repeat steps 1 through 10 for
remaining cabinets and proceed to paragraphs 2.3 and 2.4; otherwise,
proceed to step 18.
18.
Secure cabinet to floor with contractor supplied hardware and proceed to
paragraph 2.2.5.
2--8
Powerware 9330 (10 kVA- -40 kVA) Installation and Operation
164201300 REV. G 061502