At the end of the activation phase the
steam injection system will need to be
cleaned to remove all traces of
descaling solution.
Cleaning is carried out by flushing
approx. 1 litre of fresh tap water
through the system. The water is
collected in the universal tray. This
process is repeated three times.
Messages will appear in the display
with advice about the rinsing process.
M Take the universal tray out of the
oven and empty it. Place the tray
back in the oven again on the top
shelf level.
N Detach the plastic tube from the
container.
O Rinse the container and fill with
approx. 1 litre of fresh tap water.
P Place the container back in the oven,
insert the plastic tube, secure it to
the container and close the door.
Q Touch "OK".
Cleaning and care
The intake process for the first rinse
starts.
Water will be flushed through the steam
injection system and will then collect in
the universal tray.
Messages will appear in the display
with advice about the second rinsing
process.
R Take the universal tray out of the
oven and empty it. Place the tray
back in the oven again on the top
shelf level.
S Remove the plastic tube from the
container. Rinse the container and fill
it with approx. 1 litre fresh tap water.
T Place the container back in the oven,
insert the plastic tube, secure it to
the container and close the door.
U Touch "OK".
V Do the same for the third rinsing
process.
Leave the universal tray (with the
water which has collected in it) on the
top oven shelf whilst the evaporation
process takes place.