These steps summarize your switch installation. The rest of this chapter
provides details on these steps.
1.
Prepare the installation site
environment into which you will be installing the switch is properly
prepared, including having the correct network cabling ready to connect
to the switch and having an appropriate location for the switch. See
2-3
for some installation precautions.
2.
Verify the switch passes self test
power source and observe that the LEDs on the switch's front panel
indicate correct switch operation.
3.
Mount the switch
Switches can be mounted in a 19-inch telco rack, in an equipment cabinet,
on a wall, under a table, or on a horizontal surface. The switches can also
be mounted on a wall, under a table, or on a horizontal surface.
4.
Connect power to the switch
plug it into the main power source.
5.
Connect the network devices
network cables, connect the network devices to the switch ports.
At this point, your switch is fully installed. See the rest of this chapter if you
need more detailed information on any of these installation steps.
(page
2-5). Make sure the physical
(page
(page
2-8). The V1410-16, V1410-24, and V1410-24-2G
2-14). Once the switch is mounted,
(page
(page
2-16). Using the appropriate
2-6). Plug the switch into a
page

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents