Slide the Aligner into place, loosely attach the "4" Pan Head Screws with the "4" Lock
Step 16:
Washers.
Check that the metal surface of the Aligner Roller Assembly is flush with the Sheet Metal surface of
the Paper Guide. A 12" metal ruler works well to check this adjustment. Slip the ruler under the green
belt and press it flat against the two surfaces. Adjust the Aligner and snug the screws when perfectly
flush.
The green belt should look like the drawing shown after step 11.
NOTE:
As a double check, hold the entire Paper Guide assembly up so that you can visually inspect the
alignment between the sheet metal surface and the metal surface of the Aligner. The Green Belt
should appear to be even or parallel, and just floating above the surface of the sheet metal.
To install the Paper Guide Assembly into the StreamPunch.
Step 17:
1.
As you slide the Paper Guide Assembly into place,
a. Hook up the Sensor Harness to the Sensor on the back.
b. Lift it up slightly to clear the lower Transition Paper Guide.
c. Be sure to clear the Sensor Bracket at the top left.
d. Be sure that the Flex Coupling Shaft is sticking out of the rear of the StreamPunch
properly.
2.
Visually check all around the mounting area of the Paper Guide Assembly and that the Sensor
Harness is properly connected.
3.
Loosely secure it in place with "3" screws on the left and "3" on the right.
4.
Loosely install the "2" top screws.
5.
Once all "8" mounting screws have been properly started you have good alignment. You may
now go back and tighten the screws until they are snug.