RAM 1000/ RAM 5500 INSTALLATION SPECIFICATIONS

WARNING
All Sliding Gate Operators are factory preset
for (LH) Left Hand Installations.
CONCRETE PAD CONSTRUCTION
Dimensions given for the pad are based on soil bear-
ing shear of 2000 P.S.F. These figures may have to
be adjusted depending on local soil conditions.
1. Construct form for mounting pad according to
dimensions shown in Figure 6, 7 and 8.
2. Locate mounting pad according to dimensions
given in illustration.
3. Level top edge of form.
4. Set reinforcing bars and wire mesh.
5. Mix concrete, pour mixture into form. Level and
finish surface after pouring is complete.
6. Allow pad to cure for 48 hours, and remove forms.
Figure 7
concrete
8 5/8"
18"
OPERATOR
C L
GATE
6"
8
Do not exceed the specifications. The warranty on your unit will be void if the
installation exceeds the recommended specifications.
TOP vIEW
GATE ShOWN CLOSED
Lh
FRONT INSTALLATION
concrete
Mark centers and
18"
install four 1/2-13
UNC Red-head
13 1/4"
Anchor Bolts
BASE
4 1/2"
3" MIN
4"
TAIL
Wall
24"
Figure 6
Figure 8
www.ramsetinc.com
TOP VIEW
SHOWN OPEN