Table of Contents Table of Contents Safety Information .............................. v General Installation Process ..........................1 Before You Begin ............................2 Tools and Supplies needed ........................2 System Reference ..........................2 Cable Routing ............................... 2 Installing a Hot-swap Hard Disk Drive ....................2 Installing a Hard Disk Drive into 3.5”...
Page 4
Figure 11. Installing the power supply module ..................... 6 Figure 12. Removing the power supply module ....................7 Figure 13. Installing the Rack Hand ........................7 ® Figure 14. Connecting Intel Storage System JBOD 2000 Family to RAID controller ........8...
Read all caution and safety statements in this document before performing any of the instructions. ® ® See also Intel Server Boards and Server Chassis Safety Information on the Intel Server Deployment Toolkit 3.0 CD and/or at http://www.intel.com/support/motherboards/server/sb/cs-010770.htm. Wichtige Sicherheitshinweise Lesen Sie zunächst sämtliche Warnund Sicherheitshinweise in diesem Dokument, bevor Sie eine...
Page 6
Safety Information Warnings Heed safety instructions: Before working with your product, whether you are using this guide or any other resource as a reference, pay close attention to the safety instructions. You must adhere to the assembly instructions in this guide to ensure and maintain compliance with existing product certifications and approvals.
General Installation Process Before You Begin Before working with your server product, pay close attention to the Safety Information at the beginning of this manual. Note: Whenever you service the system, you must first power down the server and unplug all peripheral devices and the power cord.
General Installation Process Installing a Hard Disk Drive into 3.5” Hard Drive Carrier 1. Remove the drive carrier by pressing the green button and opening the lever (see letter A). Slide the carrier out (see letter B). Figure 1. Installing Hard Disk Drive – Removing 3.5” HDD carrier 2.
General Installation Process For installing 2.5” Hard Disk Drive as an option: A. Break off the tab on the HDD interface bracket (see letter d1). B. Install the HDD interface bracket from top. C. Secure the bracket with three screws as shown (see letter d2). D.
General Installation Process Installing a Hard Disk Drive into 2.5” Hard Drive Carrier 1. Remove the drive carrier by pressing the green latch to unlock (see letter A). Pull out the black lever and slide the carrier out (see letter B). Figure 6.
General Installation Process 4. With the lever open, insert the hard disk drive assembly into the chassis, then push in the lever to lock it into place (see letter F). Figure 9. Installing Hard Disk Drive – Inserting 2.5” HDD assembly Installing Second Power Supply Module (Optional) 1.
General Installation Process Note: To remove a power supply module, push the green latch in the direction shown while pulling out of the system by the handle. Figure 12. Removing the power supply module Installing the Rack Handles Note: Rack handles are required to install the bezel. For detailed instructions, see the Service Guide. Figure 13.
Finishing Up ® Before using this Intel Storage System JBOD 2000 Family, you must finish making I/O connections and plug in the power cord(s). 1. Verify that the system top cover is installed. 2. Install the server into the rack using the instructions provided with the rack mounting kit.