Installation flow
Figure 18 Installation flow
Install the switch to a rack
Install power supplies
Check before installation
Check the following before installing an H3C S12500 switch:
•
Make sure that you have read "Preparing for Installation" carefully and the installation site meets all
the requirements.
Using the packing list supplied with your switch, inspect the switch to be sure that you have all the
•
items listed in the packing list, and verify that the switch was not damaged during shipment. If
anything is damaged or missing, contact the sales agent or customer representative immediately.
For regulatory compliance and safety information, see "Regulatory Compliance and Safety
•
Information".
Installing the switch in a rack
This section includes these topics:
•
Installation preparation
Installing slide rails and cage nuts to the rack
•
Installing the mounting brackets
•
Start
Determine the
installation site
Install the switch to a workbench
Ground the switch
Install fan trays
Connect the power cords
Verify the installation
End
Install cards
26