Quadra-Fire REMINGTON QFP40 Operation Manual page 41

Direct vent gas fireplace
Table of Contents

Advertisement

REMINGTON QFP40 Direct Vent FIREPLACE
VERTICAL INSTALLATION INSTRUCTIONS (CONT.)
Step 1. Follow installation Steps 1 and 2 under vertical termination section.
Step 2. Using the plumb-bob, mark the centerline of the venting system on the ceiling,
and drill a small hole through the ceiling and roof at this point. From the roof,
locate the drill hole and mark the outline of the cathedral ceiling support box.
Step 3. Remove shingles or other roof covering as necessary to cut the rectangular
hole for the support box. Cut the hole 1/8" (3mm) larger than the support box
outline.
Step 4. Lower the support box through the hole in the roof until the bottom of the box
protrudes at least 2" (51mm) below the ceiling (Figure 17). Align the support box
both vertically and horizontally with a level. Temporarily tack the support box in
place through the inside walls and into the roof sheathing.
FIG. 17
Step 5. Using tin snips, cut the support box from the top corners down to the roofline,
and fold the resulting flaps over the roof sheathing (Figure 18). Before nailing it
to the roof, run a bead of non-hardening mastic around the top edges of the
support box to make a seal between it and the roof. Clean out any combustible
material from inside the support box.
FIG. 18
Step 6. Complete the cathedral ceiling installation by following the same procedures
outlines in steps 4 through 8 for vertical terminations.
250-4721 JUNE 2001
CATHEDRAL CEILING INSTALLATION
Page 41

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents