V-Plow Assembly
GENERAL INFORMATION
WARNING: To prevent personal injury
or death, be certain to keep clear of
any parts that may drop when remov-
ing bundling straps, wires or brackets. Sup-
port heavy sections with hoist or blocks be-
fore removing wires or straps.
In the following instructions, left and right ma-
chine references are defined as being viewed
from the cab of the truck.
Be certain that hydraulic hoses and electrical
wires are safely routed and allow full motion of
moving parts. Secure loose wires with plastic tie
straps.
Some components are fastened at incorrect lo-
cations for shipping purposes.
All hardware should be tightened only enough
to ensure safety during assembly. Torque hard-
ware to specified values, as shown in the fol-
lowing chart, only after assembly has been com-
pleted.
GRADE 5 TYPE B & F LOCK NUT TORQUES
Size
Ft-lbs.
5/16"
3/8"
1/2"
5/8"
117-165
GRADE 5 BOLT TORQUES*
Size
Ft-lbs.
1/4"
3/8"
1/2"
73-103
5/8"
146-206
* applications without lock nuts
Replace
worn
bolts
grade 5 bolts and equivalent type B and type F
lock nuts. Type B lock nuts are plain hex; type F
lock nuts are flanged hex.
PLOW ASSEMBLY
N-m
13-18
17-25
23-33
31-44
58-82
79-112
158-223
N-m
8-12
11-16
29-41
39-56
99-140
198-279
and
lock
nuts
1.
Lift the snowplow moldboard assembly to
a clear level working area by hooking hoist
chains through the two holes in the top plate
of the center mast. The hoist should be ca-
pable of lifting at least 1,000 lb. loads.
Remove two side markers and 5/16 inch
hardware from the top of the moldboard,
and set aside for assembly later. Save two
sets of 5/16 inch hex bolts, flat washers and
lock nuts from the shipping brackets for as-
sembling the side markers.
2.
Open the frame crate and set aside the
power unit box, headlamp boxes and parts
boxes for later assembly. Remove the frame
assembly from the shipping crate to a piece
of cardboard or other padding that will pre-
vent scratches in the paint.
Locate the 3/4 inch X 4-1/4 inch hex bolt,
3/4 inch nylon insert lock nut and one 90
O-ring/flare hydraulic fitting in the hardware
bag in the parts box.
Install the O-ring end of the 90
the lift cylinder port so that the flared end
points toward the rod end when tightened.
Swing the lift frame up to its approximate
working position and hold with a hoist or
forklift.
Bolt the upper lift links to the outside of the
two lugs on the lift frame, then pin the lower
end of the lift cylinder between the two lugs
on the frame assembly with the hardware
provided.
with
PLOW ASSEMBLY
DWG NO. 4169A
O
fitting into
O

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

V-plow 1951

Table of Contents