Carrier 19FA Series Installation Instructions Manual page 27

50/60 hz hermetic centrifugal liquid chillers hfc-134a
Hide thumbs Also See for 19FA Series:
Table of Contents

Advertisement

Figure
15,
Figure
16, and
within the compressor terminal box. For the purposes of illustration, the terminal insulation has
been omitted.
Important: Do not insulate terminals until wiring arrangement has been checked and
approved by Carrier start-up personnel. Also, make sure correct phasing is followed
for proper motor rotation.
Insulate Motor Terminals and Lead Wire Ends
Insulate compressor motor terminals, lead wire ends, and electrical wires to prevent moisture
condensation and electrical arcing. For low-voltage units (up to 600 v), obtain insulation
material from machine shipping package consisting of 3 rolls of insulation putty and one roll of
vinyl tape.
1. Insulate each terminal by wrapping with one layer of insulation putty.
2. Overwrap putty with 4 layers of vinyl tape.
Click here for Figure 15 — Compressor Terminal Arrangement 18-Lead, Rear Inlet
Figure 17
illustrate 3 methods for assembling multiple lead wires