Page 1
Instruction Manual for model PCH 18 Wall mounted heat only boiler Premix condensing system boiler This appliance must be installed by a licensed and/or qualified technician. Failure to properly install this appliance could result in property damage and possible injury or death to occupents.
CONTENTS Pages 1. General information 1.1 General warnings 1.2 Product conformity 2. Technical characteristics 2.1 Technical data 2.2 Dimensions 2.3 Internal parts of the boiler 2.4 Water circuit 2.5 Circulation pump head/flow graph 2.6 Printed circuit board – Technical characteristics 2.7 Control panel 3.
Page 4
CONTENTS Pages 6. Maintenance (authorized personnel) 6.1 General warnings 6.2 Boiler inspection 6.3 Accessing the boiler 6.4 Flushing out the primary side 6.5 Draining the central heating system 6.6 Maintenance operations 6.7 Wiring diagrams 6.8 Troubleshooting 6.9 Diagnostics 6.10 Parts list...
The commissioning of the boiler and any subsequent works carried out on the appliance must be effected by an appropriately qualified technician or an approved Pensotti North America Helpline Service Centre. The appliance must be used solely for the purpose for which it has been designed and manufactured: central heating water production.
Page 6
GENERAL INFORMATION The air inflow from adjacent rooms is allowed providing that those rooms are in depression with respect to the atmosphere and that there are not fireplace or fan installed. Check the technical data reported on the packing and on the data plate located on the inside of the front casing. Also check that the burner is appropriate for the type of gas to burn.
GENERAL INFORMATION 1.2 Product conformity Pensotti North America declares that all its products are manufactured to a high specification and in compliance with the relevant standards. All PENSOTTI NORTH AMERICA boilers are CE certified and possess technical and functional characteristics that comply with the following standards: EN 483 for GAS-FIRED CENTRAL HEATING BOILERS TYPE C OF NOMINAL HEAT INPUT ≤...
INSTALLATION INSTRUCTIONS ® printed circuit board – SM20021 2.6 DIGITECH Technical characteristics Adjustments possible by service personnel only Standard (86-176°F) / reduced (77-104°F) central heating temperature Water hammer prevention function Central Heating timer - (adjustable from 0 to 7,5 minutes) Central Heating pump overrun timer Minimum Gas pressure setting Maximum Heating Load...
INSTALLATION INSTRUCTIONS 3. INSTALLATION (authorized personnel) 3.1 Reference standard Install in accordance with CEC and NEC. All wiring shall conform to CEC, NEC and local building and electrical codes. This appliance meets the requirements of: - EMC DIRECTIVE 89/336 CEE - LVD DIRECTIVE 73/23 CEE - BOILER EFFICIENCY DIRECTIVE 92/42 CEE Failure to install a gas appliance correctly and in accordance with the above norms could lead to prosecution.
STORAGE & HANDLING Please note that prior to installation the Pensotti North America boilers should be stored horizontal position with no more than three boilers to a stack; Ensure that the boilers are...
INSTALLATION INSTRUCTIONS 3.3 Installing the boiler ■ The appliance must be installed exclusively on a flat vertical solid wall capable supporting weight. ■ The boiler should be fitted within the building unless otherwise protected by a suitable enclosure i.e. garage or outhouse.
Page 17
INSTALLATION INSTRUCTIONS Direct Vent Termination Minimum Clearances A = 12” Clearance above grade, snowline, deck, porch or balcony B = 12” Clearance to window or door that may be opened C = 24” Vertical clearance to ventilated and unventilated soffit within a 2’ distance horizontally from center line of DV termination D = 12”...
INSTALLATION INSTRUCTIONS 3.4 Water connections In order to safeguard the heat exchanger and circulation pump, especially in case of boiler replacement, it is recommended that the system is hot-flushed to remove any impurities (especially oil and grease) from the pipes and radiators. Make sure that the central heating pipes are not used to earth the electrical system.
INSTALLATION INSTRUCTIONS Internal Expansion Tank Size Maximum. System Operating Temperature (F) Maximum System Water Content (gal.)* *Assuming the air pressure in the diaphragm tank is equal to the minimum operating water pressure in the system. Central heating circuit In order to prevent scaling or deposits in the primary heat exchanger, the mains supply water to the heating circuit must be treated according to the requirements of local standards.
Page 20
INSTALLATION INSTRUCTIONS 3.5 Condensate drain FAILURE INSTALL CONDENSATE Termination to an internal soil and vent pipe DISCHARGE PIPEWORK CORRECTLY WILL AFFECT THE RELIABLE OPERATION OF THE Boiler BOILER The condensate discharge pipe MUST NOT RISE at any point along its length. There MUST be a fall of AT LEAST 2.5°...
INSTALLATION INSTRUCTIONS 3.7 Gas Connection The connection to the gas supply must be carried out by professionally qualified personnel in accordance with relevant standards: When connecting the boiler to the gas supply pipe, only use appropriate washers and gas fittings. The use of hemp, Teflon tape and similar materials is not allowed.
The connection to the mains power supply must be carried out by professionally qualified personnel, registered in accordance with current legislation and authorized by Pensotti North America. Always check to make sure that the appliance has an efficient earth ground. This requirement is only satisfied if it has been properly connected to an efficient earth system installed in accordance with the requirements of current safety standards and carried out by professionally qualified personnel.
Page 23
INSTALLATION INSTRUCTIONS Wire connections Connect the power supply to the terminal board inside the control panel as follows: a. Switch off the power supply at the main switch. b. Remove the front case panel of the boiler. c. Slacken the screws and remove plate A (see fig. 1). d.
Page 25
INSTALLATION INSTRUCTIONS The standard flue components above are suitable for horizontal and vertical applications. Maximum permissible equivalent flue lengths are; Horizontal: 8 meters / 26 feet Vertical: 8 meters / 26 feet Any additional turns in the flue system must be taken into consideration. Each elbow decreases the equivalent length as shown.
INSTALLATION INSTRUCTIONS 4. COMMISSIONING THE APPLIANCE 4.1 General warnings The following operations must be carried out by professionally qualified personnel, registered in accordance with current legislation. The boiler leaves the factory pre-set and tested for burning either natural Gas or LPG. Nevertheless, when starting the boiler for the first time, make sure that the information on the rating plate corresponds to the type of gas being supplied to the boiler.
INSTALLATION INSTRUCTIONS 4.2 Filling the system Use only clean tap water to fill the system. Once the water pipes have been connected, close the AIR VENT VALVE gas feed valve and fill the system as follows: Check that the circulation pump runs freely; AIR VENT VALVE PLUG Check that the plug of the air vent valve has been PUMP...
INSTALLATION INSTRUCTIONS 4.3 Flushing the system Failure to flush and add inhibitor to the system will invalidate the appliance working. All systems must be thoroughly drained and flushed out using additives – corrosion inhibitors and flushing agents/descalers. To flush out the primary side of this unit. a.
INSTALLATION INSTRUCTIONS 4.5 Starting up the boiler Once the system has been filled, proceed as Table n°1 follows: Gas type Check that the exhaust flue is free of Methane - G20 obstructions and correctly connected to the boiler; Liquid Propane Gas - G 31 10.1 Switch on the power supply to the boiler;...
REGULATION INSTRUCTIONS 5. REGULATING THE APPLIANCE 5.1 Parameters table PARAMETER TYPE OF OPERATION PARAMETER VALUE FUNCTION N° Instantaneous Boiler with storage tank Selects the type of boiler B. w/storage tank Comfort (+13°F) D.H.W. Temperature 95-160 °F Natural gas Selects the type of gas Sets the central heating Standard (86-176°F) temperature...
REGULATION INSTRUCTIONS 5.2 Setting the parameters To modify the preset values of the parameters reported in the previous table, open the parameter settings menu as follows: 1. Place the On/Off switch in the OFF O FF position. 110V 60Hz 2. Activate the On/Off switch while keeping P 00 buttons „+‟...
Page 32
REGULATION INSTRUCTIONS To enter the parameters menu, follow the previously described procedure (steps 1-5). 1 – T ARAMETER YPE OF BOILER 6. Use buttons „+‟ and „-„ to modify the value of the 110V 60Hz parameter: 00 = Instantaneous boiler 01 = Storage boiler;...
Page 33
REGULATION INSTRUCTIONS 4 – C ARAMETER ENTRAL HEATING PUMP 6. Use buttons „+‟ and „-„ to modify the value of the parameter: 110V 60Hz 00 = standard (3” overrun) 01 = permanent (always running) 7. Press and release button „S‟ to confirm. The parameter number (4) will appear on the display.
Page 34
REGULATION INSTRUCTIONS 7 – C ARAMETER ENTRAL HEATING PUMP OVERRUN TIMER 6. Use buttons „+‟ and „-„ to modify the value of the parameter within the prescribed limits 110V 60Hz 00 = 0 x 5” = 0” 90 = 90 x 5” = 450” (7.5 min) The default value is 36 = 180”...
Page 35
REGULATION INSTRUCTIONS 13 – D.H.W ARAMETER PRIORITY Not applicable 110V 60Hz P 1 3 110V 60Hz 14 – T ARAMETER YPE OF BURNER 6. Use buttons „+‟ o „-‟ to modify the value of the parameter: 110V 60Hz 00 = boiler with atmospheric burner; 01 = boiler with premix burner 25 kW;...
Page 36
REGULATION INSTRUCTIONS 17 – M ARAMETER INIMUM PEED ETTING 6. Use buttons „+‟ o „-‟ to modify the value of the parameter between: 110V 60Hz min = 33 Hz ; max = value of parameter 18 The default value is : - 38 Hz for Natural Gas;...
Page 37
REGULATION INSTRUCTIONS 21 – I ARAMETER GNITION EQUENCE ETTING 1 1 0 6. Use buttons „+‟ o „-‟ to modify the value of the 110V 60Hz parameter between: min = value of parameter 17; max = value of parameter 18. The default value is: - 90 Hz for Natural Gas;...
REGULATION INSTRUCTIONS 5.3 Gas data Technical data tables Table no.1 - CO2 Values Gas type Natural gas - G20 Liquid Propane Gas - G 31 10.1 Table no.2 - Frequency PARAMETRO 20 17-19 ARAMETER ARAMETER Gas type Maximum Central Minimum (Hz) Maximum D.H.W.
The conversion of a boiler from burning natural gas to LPG, or vice versa, must be carried out exclusively by professionally qualified personnel, registered in accordance with current legislation and authorized by Pensotti North America. Check that the gas supply pipe is suitable for the new fuel type.
6. MAINTENANCE (authorized personnel) 6.1 General Warnings All maintenance operations must be carried out by professionally qualified personnel, authorized by Pensotti North America. The frequency of boiler maintenance must comply with current law and, nevertheless, should be carried out once a year.
MAINTENANCE INSTRUCTIONS 6.3 Accessing the boiler All maintenance operations require one or more of the boiler casing panels to be removed. The side panels can only be removed after the front panel has been removed. Front panel: Remove the fixing screws at the lower edge of the front panel.
MAINTENANCE INSTRUCTIONS 6.5 Draining the central heating system If the need arises to drain the system, this can be done as follows: Switch the system to “WINTER” mode and ignite the boiler. Switch off the power supply to the boiler. Wait for the boiler to cool down.
Before carrying out any cleaning or part replacement operations, ALWAYS turn off ELECTRICITY, WATER primary heat supplies to the boiler. exchanger Pensotti North America will not be held responsible for damage to any of the premix burner unit boiler’s components caused non- compliance with this instruction.
Page 44
MAINTENANCE INSTRUCTIONS and exhaust joints are tight. Part replacement Ignition and/or flame detection electrodes (see fig. 1) ignition Un-Plug the electrode wires; electrode Slacken the fixing screws; Remove the electrodes. When fitting the new ones, check that the seals are not damaged. Replace if necessary; Reconnect the wires and re-assemble the components following the above procedure in reverse order;...
Page 45
MAINTENANCE INSTRUCTIONS Safety thermostat (see fig. 2) Disconnect the connecting wire; Unscrew the fixing screws and remove the thermostat; Replace thermostat re-assemble components following the above procedure in reverse order; Switch on the electricity, water and gas supplies and restart the appliance. heating sensor Heating sensor...
Page 46
MAINTENANCE INSTRUCTIONS Electric fan (see fig. 1) Remove and dismantle the entire burner unit (see “Cleaning the burner unit”). venturi Use an 8 mm spanner to unscrew the four nuts securing the electric fan to the gas manifold and then remove the electric fan, noting the positions of the washer and diaphragm.
Page 47
MAINTENANCE INSTRUCTIONS Circulating pump (motor body) (see fig. 1) Close the shut-off valves and drain the central heating circuit of the boiler; circulating Use a 5 mm Allen key to unscrew the four screws pump securing the motor body to the impeller body; Remove the motor body and check the condition of the washer.
Page 48
INSTALLATION INSTRUCTIONS Primary heat exchanger (see fig. 1) Close the shut-off valves and drain the central primary heat heating circuit of the boiler; exchanger flue connection Switch off the power and gas supply to the boiler; chamber Remove and dismantle the entire burner unit (see “Cleaning the condensation module and burner unit”);...
Page 50
INSTALLATION INSTRUCTIONS Connecting the room thermostat (Option) Connect the wires to the terminal board inside the instrument panel as follows: (Example with WEEK digital weekly chronostat): a. switch off the power supply at the main switch. b. remove the front case panel of the boiler. c.
Page 51
INSTALLATION INSTRUCTIONS Connecting the remote controller the outside temperature sensor (option) Connect the wires to the terminal board inside the instrument panel as follows: a. switch off the power supply at the main Outside temperature switch. sensor (option) b. remove the front case panel of the boiler.
Page 52
INSTALLATION INSTRUCTIONS Remote control and zone valves wiring For the installation of a zone valve p.c.b, it is necessary to access the main p.c.b for electrical connection (see 6.3 “Accessing the boiler” ) and to activate the parameter no. 16 (see 5.1 “Parameters table”).
Page 53
INSTALLATION INSTRUCTIONS Remote control, zone valves and telephone control wirings...
Page 54
INSTALLATION INSTRUCTIONS Regulating the Flow temperature in accordance with the outdoor temperature The outdoor sensor has to be connected directly to circuit board SM20021. The sensor can thus be managed in one of two ways: In case of remote controller + outdoor temperature sensor installation, the climatic compensation curve is set by the remote itself (see remote control installation and operating manual).
INSTALLATION INSTRUCTIONS 6.8 Troubleshooting ERROR PROBLEM POSSIBLE CAUSE REMEDY CODE WITH NO IGNITION CHECK GAS SUPPLY. NO GAS. REPLACE PART. IGNITION ELECTRODE BROKEN OR REPLACE PART EARTHED. REGULATE MECHANICAL MINIMUM OR GAS VALVE MALFUNCTION SLOW IGNITION. MECHANICAL MINIMUM ADJUSTMENT CHECK THE MAXIMUM PRESSURE (ON GAS VALVE) SET TOO LOW OR SLOW SETTING.