Installation; Starting Switch Up; Hardware And Cable Installation - LevelOne GSW-0890 User Manual

8-port 10/100/1000mbps w/ 2-port sfp l2 managed switch
Hide thumbs Also See for GSW-0890:
Table of Contents

Advertisement

2. Installation

2-1. Starting switch Up

This section will give users a quick start for:
-

Hardware and Cable Installation

-
Management Station Installation
-
Software booting and configuration
2-1-1. Hardware and Cable Installation
At the beginning, please do first:
⇒ Wear a grounding device to avoid the damage from electrostatic discharge
⇒ Be sure that power switch is OFF before you insert the power cord to power
source
Installing Optional SFP Fiber Transceivers
Note: If you have no modules, please skip this section.
Fig. 2-1 Installation of Optional SFP Fiber Transceiver
Connecting the SFP Module to the Chassis:
The optional SFP modules are hot swappable, so you can plug or unplug it
before or after powering on.
1. Verify that the SFP module is the right model and conforms to the chassis
2. Slide the module along the slot. Also be sure that the module is properly
seated against the slot socket/connector
3. Install the media cable for network connection
4. Repeat the above steps, as needed, for each module to be installed into
slot(s)
5. Have the power ON after the above procedures are done
8

Advertisement

Table of Contents
loading

Table of Contents