4.1
Unpacking the delivery unit
I
For a description to unpack the PRIMECENTER M1 19-inch rack please
refer to the info-sheet delivered with the rack.
4.2
Rolling off the PRIMECENTER M1 19-inch
rack from the transport palette
I
For a description to roll off the rack from the transport palette please refer
to the info-sheet delivered with the rack (also available on the web:
http://manuals.ts.fujitsu.com/file/10279/pcrm1-qsg-unpack-muli.pdf).
4.3
Setting up the PRIMECENTER M1 19-inch
rack
I
For a description to set up the rack from the transport palette please refer
to the info-sheet delivered with the rack (also available on the web:
http://manuals.ts.fujitsu.com/file/10279/pcrm1-qsg-unpack-muli.pdf).
Introduction
To ensure that the rack has a firm foothold, it is necessary to align it in all 3 axis
exactly horizontal.
Required tools
The following tools are required to perform this task:
– Hexagon key 6 mm
– Spirit level
Unpacking and checking the delivery unit