7.3.7.3
Installation options for 600 mm wide symmetrical racks
Rack height Installation direction
vertically
42 HU
Not possible
24 HU
Not possible
16 HU
Not possible
Table 22: Installation options for 600 mm wide symmetrical racks
Performing the task
Ê Install the socket strips onto the PDU kit 2 HU / 3 HU as described on
page
73.
Figure 73: Socket strip extension 3 safety plugs and assembly mounted in a 600 mm wide
symmetrical rack
Ê Install the PDU kit 2 HU / 3 HU into the rack on the desired height.
I
The PDU kit 2 HU / 3 HU has to be installed from HU 7 upwards.
Power Distribution
Installation direction
horizontally
Max. 4x with PDU kit 2 HU / 3 HU
Max. 4x with PDU kit 2 HU / 3 HU
Max. 4x with PDU kit 2 HU / 3 HU
105