Test Run - Grizzly G0755 Owner's Manual

Heavy-duty mill/drill w/stand & power feed
Table of Contents

Advertisement

Test Run

the purpose of the test run is to verify that the
machine functions properly and is ready for regu-
lar operation.
Before beginning this procedure, make sure: (1)
you understand the safety instructions at the
beginning of this manual, (2) the machine is set
up properly, and (3) all tools and objects used dur-
ing setup are cleared away from the machine.
IMPORTANT: if the machine or its components
do not function as described, or if the machine
has unusual noises or vibrations, immediately turn
it OFF and disconnect power.
For your convenience, a Troubleshooting table
is provided on Page 35. if you cannot find a rem-
edy, contact our tech support at (570) 546-9663
for assistance.
To test run the machine:
1.
push emergency stop button (see Figure 9).
power
Lamp
spindle
Forward
spindle
stop
Figure 9. Control panel.
2.
rotate elevation power Feed switch to oFF.
3.
Connect machine to power source by insert-
ing power cord plug into matching recep-
tacle—the power Lamp should light after
connection.
Model G0755 (Mfg. Since 1/13)
elevation
power
Feed
spindle
reverse
emergency stop
4.
twist emergency stop button clockwise until
it pops out—this resets the switch so the
machine can be started (see Figure 10).
Figure 10. resetting the switch.
5.
push spindle Forward button to start machine.
A correctly operating machine runs smoothly
with little or no vibration or rubbing noises.
6.
press emergency stop button to stop
machine.
7.
Without resetting emergency stop button,
press spindle Forward button—the machine
should not start.
—if the machine does start (with the
emergency stop button pushed in), imme-
diately disconnect machine from power.
the emergency stop button safety feature
is not working correctly. this safety feature
must work properly before proceeding with
regular operations. Call tech support for
help.
8.
reset emergency stop button and use
elevation power Feed switch to raise and
lower headstock.
the test run is complete. Before beginning any
regular operations, perform the Spindle break-In
procedure on the next page.