8.
Install the remaining #10-32 x 5/8 Phillips pan-head screws into the upper left and lower right
holes to complete the installation. See
Figure 2-15 Securing the Switch
9.
Provide power to the switch by connecting the power cord to the switch power supply and to a
power outlet. Ensure the power cord is routed so that it is not exposed to stress. Power is
supplied to the switch as soon as the cord is connected. The switch runs POST (power on
self-test) by default each time it is turned on.
Note:
Installation and Reference Guide
Do not connect the switch to the network until the IP address is correctly set. For
instructions on how to set the IP address, see
page
2-16.
Installing and Configuring the Switch
Figure
2-15.
Configuring and Connecting the Switch
2
on
2-15
Need help?
Do you have a question about the StorageWorks 8B - FC Entry Switch and is the answer not in the manual?
Questions and answers