Page 3
YOU MUST READ THIS DOCUMENT BEFORE YOU BEGIN TO ASSEMBLE THE SHELTER. Thank you for purchasing our shelter. When properly assembled and maintained, this product will provide years of reliable service. These instructions include helpful hints and important information needed to safely assemble and properly maintain the shelter.
Page 4
ANCHORING THE CONTAINER Make sure you have: Welder. Cement. Four 3” x 3” x 6 feet ¼” Square steel angle As shown in the diagram 1, make a 3 ft deep hole right beside one of the front and opposite rear corners of the container, in which the 6ft square steel will be installed.
Page 5
Highly Recommended 1. All container canopy covers need to be removed during windstorm of 60 mph, leaving frame assembled. Customer responsibility. 2. All container canopy covers need to be removed before a snowstorm of 1-2 inches (for single truss Shipping container roofs) and 3-4 inches (for double truss Shipping container roofs), leaving the frame assembled.
Page 6
60'x40'x15' Parts List Part Qty/ Description Code Roof Top Truss Arch Upper Truss Arch A-10pcs Middle Truss Arch B-8pcs Lower Truss Arch Base Plate left & right, four corners with ratchet A-12pcs Base Plate, inner with ratchet B-2pcs Purlin Lower Tensioning Tube for Roof 2 sets Cover, (4+1) pcs/set Connection Plate for steel wire No.21...
Page 7
Knitting Rope for roof cover (4 1 pack bundles) Belt for ratchet Roof Cover Felt Piece (self adhesive ) Cable Tie for fixing felt No.17 Expansion Bolt Turnbuckle for steel wire No.21 Turnbuckle for steel wire No.21A Steel Wire Clamp Steel Wire between arches Steel Wire on roof top, 1+1 pc/set 9 sets...
Page 8
INSTALLATION PROCESS Note: Make sure to fix the container firmly before installing the shelter. A—BASE PLATES INSTALLATION Please refer to the diagram (Figure 1) to mark the position of base plates Figure 1 1. The measurement is done as the above figure 1 showing. Referring to the above diagram and confirm the place of base plates.
Page 9
B—FRAME INSTALLATION 1. Arch Installation: Find Truss Arches (No.1, 2, 3, 4) and Base Plate (No.5 & 6) and connect them by High Strength Bolt M14x35 (No.10). 2. Install Steel Wire (No.21A) on the roof top by Turnbuckle (No.19A) and Steel Wire Clamp (No.20).
Page 11
2. When finish installing all arches, lift the arch to top of containers, and then adjust the distance between arches. Weld the base plate to container firmly. 3. Install Purlin (No.7) by Bolt M10x70 (No.11) and then the third arch and Purlins. In this turn, one arch and then purlin tubes.
Page 12
Roof Cover Installation Now your assembly is completed.