FAULT0100
(GRID RELAY
FAULT)
FAULT0110
(BUS
IMBALANCE)
FAULT0130
(BUS OVER
TOTAL
VOLTAGE)
FAULT0150
(OPEN-LOOP
SELF-CHECK
FAILURE)
The actual display wording of "PVxVoltOver" is "PV1VoltOver" or "PV2VoltOver" or "PV3VoltOver".
The actual display wording of "PVxReverse" is "PV1Reverse" or "PV2Reverse" or "PV3Reverse".
The actual display wording of "PVxOvercurrent" is "PV1 Overcurrent" or "PV2 Overcurrent" or "PV3Overcurrent".

9. Maintenance and Decommissioning of Inverters

This section defines the activities required to properly maintain the inverter and must be done by qualified
personnel who are trained in the installation, decommissioning and maintenance of PV inverters.
DOCR-071086-C (04/12/2024)
Recommended solutions:
1. Restart inverter by turning both AC and DC switches OFF. Wait for 1
minute for all energy to discharge and turn both switches ON.
2. If inverter cannot clear fault, replace inverter.
Recommended solutions:
1. Raise limit of IDCmax (for example, 400mA) to allow inverter
more room to adjust in transient condition to cope with
imbalance of impedance and voltage between grid phases.
2. If alarm still occurs after adjustment, replace inverter.
Recommended solutions:
1. Restart inverter by turning both AC and DC switches OFF. Wait for 1
minute for all energy to discharge between OFF and turn both
switches ON.
2. If inverter cannot clear fault, replace inverter.
Recommended solutions:
1. Restart inverter by turning both AC and DC switches OFF. Wait for 1
minute for all energy to discharge and turn both switches ON
2. If inverter cannot clear fault, replace inverter.