Step 10: Enphase Energy System configurations

The Enphase Energy System with IQ8P Microinverters can be used to form the PV solar grid-
tied configuration.
Enphase Energy System PV solar grid-tied
For grid-tied mode, after the IQ8 Microinverter installation, energize the system as follows:
A. Turn ON the AC disconnect or circuit breaker for the branch circuit.
B. Turn ON the main utility-grid AC circuit breaker. Your system starts producing power after
a five-minute wait time.
C. Check the LED on the connector side of the microinverter.
LED color
Flashing green
Flashing orange
Flashing red
Solid red
21
Indicates
Normal operation. AC grid function is normal, and there is communication
with the IQ Gateway.
The AC grid is normal, but there is no communication with the IQ Gateway.
The AC grid is either not present or not within the specification.
There is an active "DC Resistance Low, Power Off Condition" To
reset, refer to
DC Resistance Low – Power Off
© 2024 Enphase Energy Inc. All rights reserved.
Enphase IQ8P Microinverters
Condition.
January 2024
IOM-00002-1.0

Advertisement

Table of Contents
loading

Table of Contents