Figure 5-9 Preparing a cord end terminal
(1) Cable
Step 2 Install DC output power cables.
1.
2.
3.
----End
5.4 Installing Cables for an Intelligent Power
Distribution Unit
Procedure
Step 1 Install power cables for the intelligent power distribution unit.
Issue 01 (2021-05-30)
Insert a flat-head screwdriver (2 mm wide) into the holes for DC output
circuit breakers.
Connect DC output power cables to the corresponding DC output circuit
breakers.
Remove the flat-head screwdriver.
Figure 5-10 Installing DC output power cables
(1) DC load
NO TE
The methods for installing cables between the intelligent power distribution unit and other
power subracks are similar. The following uses one of them as an example.
Copyright © Huawei Technologies Co., Ltd.
(2) Cord end terminal
5 Installing Cables
(3) Crimping tool