Initialization Check

To determine if the system is initializing correctly, only the first chassis, GCD-CP10, one GGCD-8DLCA, and
terminals should be installed on the system. After initialization, all the terminals assigned to the GGCD-
8DLCA can be used for internal calls to one another. (By default, these stations are assigned station
numbers 200~207).

System Initialization

Before initialization is performed and verified, the entire system should be initialized.
With power OFF, all interface and option cards can be installed in the controlling chassis. The technician
can then power up the system to perform a First Initialization. After the initialization, each station display
shows default time and date indications.
For example: 12-2 Fri 10:47 AM

After Initialization

Ensure that the battery is installed in CN15 on the GCD-CP10.
Check all blade slots in software to ensure the initialization process scanned the installed hardware
correctly.
A general system operation check should be performed using default values prior to system programming.
After all previous steps are performed and any problems corrected, system programming is complete.
After System Programming is finished, the technician should perform a Second Initialization. Performing the
First Initialization a second time causes all programming memory to be lost. Second Initialization refreshes
the system RAM without losing any memory.
This completes the installation procedure for the UNIVERGE SV9100 system. The technician should check
the operation of each Multiline Terminal to ensure the system is working properly.