Installation
Post Mounted Installation Method (Using Additional Product Code APEX-SPOST)
1. Drill holes on the concrete or solid floor, four 165 * 95 holes with diameter φ 10mm
deep 50mm screws and one φ 60mm through duct hole.
2. Install and fix the anchor screws.
3. The mains cable runs through the column hole through the bottom of the column.
4. Install the backplane is fixed to the landing column with screws.
5. Attach the bracket to the charger.
6. Hang the charger into the mounting back plate and secure it.
7. Installation completed.
Note: The angle of cement ground 90°±15
1
2
Φ12 deep 60mm
Φ60mm
3
4
6
5
H
Please Note: These instructions are only applicable when using APEX-SPOST