3 Installation Method

1. Infra-red inductive controller wiring diagram:
KJR-10B
Wire controller
Infra-red inductive controller is divided into infra-red sensor and
infra-red inductive control box. When installing, you must connect
infra-red inductive control box to the wire controller, indoor unit display
panel, and infra-red sensor through CN1, CN2, and CN3 respectively.
Infra-red inductive controller
Infra-red
sensor
NIM09/E
S1
Infra-red inductive
control box
ON
Delay 1 hour to OFF the unit
1 2
ON
Delay 0.5 hour to OFF the unit
S1
1 2
ON
(Reserved switch code)
1 2
CN3
CN2
CN1
Fig.1
6
Display panel
Indoor main board
(default)