9.
Install the access panel.
10. Slide the server into the rack.
11. Connect each power cord to the server.
12. Connect each power cord to the power source.
13. Power up the server.
The installation is complete.

Installing a tertiary riser cage

Prerequisites
Before you perform this procedure, make sure that you have the following items available:
The components included with the hardware option kit
T-10 Torx screwdriver
Procedure
1. Observe the following alert.
CAUTION: To prevent damage to the server or expansion boards, power down the server and
remove all AC power cords before removing or installing the PCI riser cage.
2. Power down the server.
3. Do one of the following:
Disconnect each power cord from the power source.
Disconnect each power cord from the server.
4. Do one of the following:
Extend the server from the rack.
Remove the server from the rack.
5. Remove the access panel.
6. Remove the rear wall blanks.