9.
Verify the operation of the rack rails:
Two people might be needed for this procedure: one to slide the chassis in and out of the rack, and the other to observe
the rear panel cables and power cords.
a. Fully extend the chassis out of the rack.
b. Check that there is enough slack in the cables and cords for full extension of the chassis. Make sure that there is no
cable binding or crimping.
c. To ensure that the cables and cords are secured properly, slide the chassis in and out of the rack. Make sure that
there is no risk of accidental disconnection of the peripheral cables and power cords.
10. Slide the server into the rack until the chassis ears are flushed against the rack posts.
11. (Optional) Open the chassis ear latches (callout 1), and then tighten the shipping screws (callout 2).
The installation is complete.