User Responsibilities, Machine Preparation, and Inspection
2. Test the tower boom assembly sequencing as follows:
a. Place machine on level ground with the tower boom assembly in the stowed
position. Identify the tower boom vertical limit switch adjacent to the tower
lift cylinder at the bottom end (rear) of the tower base boom. Open the left
side hood and perform a visual check that the plunger on the tower boom
vertical limit switch is fully extended. The plunger is shown fully extended in
Figure — Tower Boom Vertical Limit Switch, page
34.