Starting/Stopping

8
8.1

Starting

8.1.1 Inspection before starting

After the maintenance or service work, inspect the following items, and then start inverter:
All connections are performed in strict accordance with relevant manual and circuit
diagram.
The coverings of the internal devices are fixed and secured.
The emergency stop button is released.
Make sure, by using suitable instruments, that there is no ground fault of the PV array.
Measure the DC, AC voltages with a multi-meter to check if the start-up conditions are
met, and ensure no overvoltage hazard.
Measure the DC voltage with multi-meter, and check if the polarity is correct.
If the inverter has been stored for more than half a year in the required storage
environment, a thorough and careful inspection is necessary before the inverter is
powered on.

8.1.2 Start Steps

When the abovementioned conditions are fulfilled, proceed as follows to start the MV
Station:
step 1 Close the upstream PV combiner box and downstream transformer switches of the MV
Station.
step 2 Close the QS6 AC maintenance switch, and QS5 DC maintenance switch.
step 3 Turn the DC knob switch to the ON position.
step 4 Stop the inverter through the touch screen.
step 5 Manually close the QS1 and QS3 DC load break switches. If the inverter was equipped with
energy storage ports,close QS2 and QS4 as well.
step 6 Perform the start operation through the touch screen, and the MV Station starts grid-
connected operation.
- - End
Specific switch position,refer to
"figure 3-1 DC
cabinet".