5.18 Making the Electrical Connections
1. Remove the cover from the control box by removing the
2 screws (Fig. 72).
2. Slide the box forward for easier access.
3. The terminal strips may be removed by carefully pulling
them forward. Connect the supply cable and the pump
cable to the terminal strips (Fig. 74).
IMPORTANT - When installing in conjunction with a
thermal store or heat store please refer to the store
manufacturers installation instructions when wiring
the boiler.
4. The pump must be connected to the boiler terminals.
5. A permanent live must be connected to the 'L terminal.
6. The switched live must be connected to the 'S/L'
terminal.
7. Clamp the cables in the grips provided. Ensure that the
lengths of the supply cables are such that the current
carrying wires become taut before the earth wires if the
cable should pull out of the cable clamp (Fig. 73).
8. Tuck the cables under the box and clip to the wall
where necessary. Make sure sufficient slack is left to allow
the box to slide forward for future access.
9. A cable clip is provided in the base of the box.