REQUIREMENTS FOR INSTALLATION OF THE PLANT - POSITIONING
The most important thing to do before installation of the boiler is to set aside a suitable area that meets the minimum requirements for
installation.
the minimum clearance in front of the product to allow suitable access for cleaning, maintenance, etc. must be 700 mm;
the minimum permissible distance between the back of the product and a wall must be 400 mm;
the minimum distance between the top of the product and a wall (ceiling) must be 600 mm to ensure easy access to the heat
exchanger for cleaning and maintenance (e.g. for removing ash and possible installation of the pellet suction kit);
the minimum clearance between the product and the wall (side) must be 300 mm.