Option 4 - Outdoor Reset With Modbus Header Sensor And Modbus Outdoor Sensor - Watts Aerco Benchmark OMM-0124 Installation And Start-Up Manual

Natural gas, propane gas and dual fuel fired modulating & condensing boilers
Table of Contents

Advertisement

Benchmark 5000-6000 Boiler Installation & Startup Manual
SECTION 6: BOILER SEQUENCING TECHNOLOGY
6.3.4 OPTION 4 - Outdoor Reset With Modbus Header Sensor And
Modbus Outdoor Sensor
OPTION 4 - Outdoor Reset With Modbus Header Sensor And Modbus Outdoor
Sensor Instructions
NOTE:
Both Header Sensor AND Outdoor Sensor must be wired. See the C-More Controller User
Manual, OMM-0032 (GF-112) and ProtoNode User Manual, OMM-0080 (GF-129) for more
information.
Step 1 - Modbus Header Sensor Wiring
Using Shielded pair 18 - 22 AWG cable, connect the Temperature Transmitter (P/N 65169)
1.
terminal Pin B to the RS485+ terminal on the I/O Box of any of the Boiler units, and Pin A of
the Temperature Transmitter to the RS485- terminal on the I/O Box of any of the Boiler
units.
2. Using Shielded pair 18 - 22 AWG cable, connect the Modbus Header Temperature Sensor
(P/N 24410) to pins 2 and 3 of the Temperature Transmitter.
3. Install a jumper wire between pins 1 and 2 of the Temperature Transmitter.
NOTES:
Polarity must be observed for the RS485 connections. The ground for the shield is at
the "SHLD" terminal in the I/O the Box.
The header sensor must be installed between 2 and 10 feet (0.61 and 3.1m)
downstream of the LAST boiler in the plant's supply water header.
There is no polarity to be observed. The ground for the shield is at the power supply
ground. The sensor end of the shield must be left free and ungrounded.
Temp Sensor P/N 24410
Step 2 - Modbus Outdoor Sensor Wiring
. If you have not already done so when installing the Modbus Header Sensor, use Shielded
1
pair 18 - 22 AWG cable to connect the Temperature Transmitter terminal Pin B to the
RS485+ terminal on the I/O Box of any of the Boiler units, and Pin A of the Temperature
Transmitter to the RS485- terminal on the I/O Box of any of the Boiler units.
2. Using Shielded pair 18 - 22 AWG cable, connect the Modbus Header Temperature Sensor
(P/N 24410) to pins 2 and 3 of the Temperature Transmitter.
3. Install a jumper wire between pins 1 and 2 of the Temperature Transmitter.
OMM-0123_E • GF-207 • 12/17/2019
Modbus Transmitter
(Continued)
Technical Support • (800) 526-0288 • Mon-Fri, 8 am - 5 pm EST
I/O Box