14.2.
Analog Input
Step
1
ATTENTION: RTP is not for use with thermocouples.
ATTENTION: RTP and cables are intended for permanent installation within their own enclosure.
Mount RTP cable assembly to ControlEdge HC900 Controller (Figure 109).
Remove appropriate key tabs from terminal block to allow mating with the module. See page 87.
Connect desired cable to AI module at controller. Choose from:
900RTC-L210
900RTC-L225
900RTC-L250
Install AI module label onto the module connector cover.
Connect shield drain wire to the grounding bars at the base of the ControlEdge HC900 rack. All
field-wiring shields must be grounded as described in the shield grounding section (page 83).
2
Mount RTP to DIN rail.
Latch to rail. See page 258.
Connect cable to RTP.
228
ControlEdge HC900 Process & Safety Controller User and Installation Manual
8 Point Analog Input
Action
Remote Terminal Low Voltage Cable Assembly, 1.0 meters long
Remote Terminal Low Voltage Cable Assembly, 2.5 meters long
Remote Terminal Low Voltage Cable Assembly, 5.0 meters long
Revision 10
May 2019