Setting the working pressure

1. Unscrew the cap 10 from the valve
bonnet 2.
2. Loosen the lock nut 7.
3. Turn the set screw 8 to the desired position
using a screwdriver / Allen key:
Turn the set screw
clockwise:
Turn the set screw
anticlockwise:
4. Observe the setting range.
Nominal
Type
size
GEMÜ N186
DN 10 - 50
DN 65 - 80
GEMÜ N086
DN 100
5. Secure the setting with lock nut 7.
The working
pressure will
increase
The working
pressure will
decrease
Setting range [bar]
0.5 - 10
1 - 6
1 - 4
29 / 36
12

Commissioning

WARNING
Corrosive chemicals!
® Risk of caustic burns!
Check the tightness of the
G
media connections prior to
commissioning!
Use only the appropriate
G
protective gear when
performing the tightness
check.
CAUTION
Protect against leakage!
Provide precautionary measures
G
against exceeding the maximum
permitted pressures caused by
pressure surges (water hammer).
Prior to cleaning or commissioning the
plant:
If the plant is new and after repairs rinse
G
the piping system with a fully opened
valve (to remove any harmful foreign
matter).
Cleaning:
The plant operator is responsible for

selecting the cleaning material and
performing the procedure.
Important:
Diaphragms set in the course of
time. After valve installation and
commissioning you must retighten
the bolts 9 or 11 diagonally.
N086, N186